Dept. of Trans. PROGRESS Serial No. Contract No. 24-235-13-44 12-0R7504 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 57% Location: Federal Project: 12-ORA-5-33.7/35.4 ACIM-052(40) Progress payment No. 002 Payment period ending: 08-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 244,342.12 174,417.12 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 23,879.00 23,879.00 4. Earned Subject to Retention 268,221.12 198,296.12 5. Mobilization 153,750.00 153,750.00 6. Total Work Completed 398,092.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 421,971.12 352,046.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 352,046.12