Dept. of Trans. PROGRESS Serial No. Contract No. 24-143-08-43 12-0R9204 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 10% Location: Federal Project: 12-ORA-90-5.1/6.7 SNHG-P090(19) Progress payment No. 002 Payment period ending: 05-20-24 INTERNATIONAL LINE BUILDERS, INC. 3955 TEMESCAL CYN RD CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 54,909.85 54,909.85 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 109,389.99 0.00 4. Earned Subject to Retention 164,299.84 54,909.85 5. Mobilization 54,193.50 18,064.50 6. Total Work Completed 109,103.35 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 208,493.34 62,974.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,974.35