Dept. of Trans. PROGRESS Serial No. Contract No. 24-200-12-51 12-0R9204 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 53% Location: Federal Project: 12-ORA-90-5.1/6.7 SNHG-P090(19) Progress payment No. 004 Payment period ending: 07-20-24 INTERNATIONAL LINE BUILDERS, INC. 3955 TEMESCAL CYN RD CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,694.99 132,350.49 2. a. Extra Work 10,187.16 10,187.16 b. Adustment Comp. 3. Materials on Hand 323,109.83 28,604.39 4. Earned Subject to Retention 661,991.98 171,142.04 5. Mobilization 68,645.10 0.00 6. Total Work Completed 407,527.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 730,637.08 171,142.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 171,142.04