Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-211-10-37 12-0R9204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-90-5.1/6.7 SNHG-P090(19) Progress payment No. 014 Payment period ending: 06-20-25 INTERNATIONAL LINE BUILDERS, INC. 3955 TEMESCAL CYN RD CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,419,472.00 0.00 2. a. Extra Work 206,063.91 18,425.00 b. Adustment Comp. 21,536.00 20,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,647,071.91 38,425.00 5. Mobilization 72,258.00 0.00 6. Total Work Completed 1,719,329.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,719,329.91 38,425.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,425.00