Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-15-29 12-0S0404 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 99% Location: Federal Project: 12-ORA-55-15.1/17.5 HSNH-P055(64) Progress payment No. 008 Payment period ending: 04-20-22 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 915,780.00 285,974.80 2. a. Extra Work 17,903.77 17,903.77 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 933,683.77 303,878.57 5. Mobilization 91,863.00 0.00 6. Total Work Completed 1,025,546.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,025,546.77 303,878.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 303,878.57