Dept. of Trans. PROGRESS Serial No. Contract No. 25-234-10-50 12-0S1104 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 34% Location: Federal Project: 12-ORA-22-R0.9/R9.4 HSNH-P022(31) Progress payment No. 010 Payment period ending: 08-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,511,584.38 1,823,628.10 2. a. Extra Work 89,024.10 0.00 b. Adustment Comp. 3. Materials on Hand 1,102,925.08 977,947.58 4. Earned Subject to Retention 11,703,533.56 2,801,575.68 5. Mobilization 2,755,000.00 0.00 6. Total Work Completed 13,355,608.48 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,458,533.56 2,801,575.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,801,575.68