Dept. of Trans. PROGRESS Serial No. Contract No. 26-299-14-38 12-0S1104 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 12-ORA-22-R0.9/R9.4 HSNH-P022(31) Progress payment No. 024 Payment period ending: 10-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #B300 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,821,241.30 885,610.10 2. a. Extra Work 684,331.80 202,706.62 b. Adustment Comp. 3. Materials on Hand 156,481.40 0.00 4. Earned Subject to Retention 26,662,054.50 1,088,316.72 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 29,405,573.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,562,054.50 1,088,316.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,088,316.72