Dept. of Trans. PROGRESS Serial No. Contract No. 22-206-14-06 12-0S2104 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 49% Location: Federal Project: 12-ORA-5-24.0/37.6 NONE Progress payment No. 003 Payment period ending: 07-20-22 J FRANCIS COMPANY 16197 KRAMERIA AVE RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 692,687.98 229,654.96 2. a. Extra Work 876.60 876.60 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 693,564.58 230,531.56 5. Mobilization 190,000.00 0.00 6. Total Work Completed 883,564.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 883,564.58 230,531.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,531.56