Dept. of Trans. PROGRESS Serial No. Contract No. 26-238-09-54 12-0S3804 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 45% Location: Federal Project: 12-ORA-5-10.0/21.3 ACIM-052(56) Progress payment No. 008 Payment period ending: 08-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,661,974.90 3,028,903.30 2. a. Extra Work 106,437.09 3,380.40 b. Adustment Comp. 3. Materials on Hand 229,133.65 -38,904.90 4. Earned Subject to Retention 13,997,545.64 2,993,378.80 5. Mobilization 2,904,726.65 0.00 6. Total Work Completed 16,673,138.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,902,272.29 2,993,378.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,993,378.80