Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-363-11-37 12-0S4804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-55-1.4/T2.1 NONE Progress payment No. 003 Payment period ending: 11-29-21 STANCE CONSTRUCTION COMPANY 9070 IRVINE CENTER DR #220 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 416,783.97 42,242.90 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 416,783.97 42,242.90 5. Mobilization 6. Total Work Completed 416,783.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 416,783.97 42,242.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,242.90