Dept. of Trans. PROGRESS Serial No. Contract No. 22-206-15-05 12-0S5904 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 94% Location: Federal Project: 12-ORA-5-1.8/44.2 NONE 12-ORA-22-2.5/12.7 12-ORA-55-10.8/15.2 Progress payment No. 004 Payment period ending: 07-20-22 CALPROMAX ENGINEERING INC 650 N ROSE DRIVE #186 PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 730,935.00 9,000.00 2. a. Extra Work 47,069.72 47,069.72 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 778,004.72 56,069.72 5. Mobilization 77,000.00 0.00 6. Total Work Completed 855,004.72 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 845,004.72 56,069.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,069.72