Dept. of Trans. PROGRESS Serial No. Contract No. 24-082-09-45 12-0S7804 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 62% Location: Federal Project: 12-ORA-73-11.0/11.3 NONE Progress payment No. 004 Payment period ending: 03-20-24 POLO ENGINEERING INC 30758 SLOAN CANYON RD CASTAIC CA 91384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 476,983.00 2,627.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 476,983.00 2,627.00 5. Mobilization 100,320.00 0.00 6. Total Work Completed 577,303.00 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 575,303.00 627.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 627.00