Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 24-163-07-52 12-0S7804 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 88% Location: Federal Project: 12-ORA-73-11.0/11.3 NONE Progress payment No. 006 Payment period ending: 05-20-24 POLO ENGINEERING INC 30758 SLOAN CANYON RD CASTAIC CA 91384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 689,095.75 148,341.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 689,095.75 148,341.25 5. Mobilization 105,600.00 5,280.00 6. Total Work Completed 794,695.75 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 794,695.75 155,621.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,621.25