Dept. of Trans. PROGRESS Serial No. Contract No. 22-332-11-20 12-0S9004 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 75% Location: Federal Project: 12-ORA-241-29.2/35.8 NONE Progress payment No. 005 Payment period ending: 11-20-22 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 477,485.00 -20,198.00 2. a. Extra Work 135,318.65 135,318.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 612,803.65 115,120.65 5. Mobilization 52,700.00 0.00 6. Total Work Completed 665,503.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 665,503.65 115,120.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,120.65