Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-097-11-38 12-0S9004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-241-29.2/35.8 NONE Progress payment No. 006 Payment period ending: 12-07-22 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 509,135.00 31,650.00 2. a. Extra Work 135,318.65 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 644,453.65 31,650.00 5. Mobilization 52,700.00 0.00 6. Total Work Completed 697,153.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 697,153.65 31,650.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,650.00