Dept. of Trans. PROGRESS Serial No. Contract No. 23-143-13-24 12-0T3404 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 53% Location: Federal Project: 12-ORA-55-13.2/17.9 NONE Progress payment No. 004 Payment period ending: 05-20-23 DOJA INC 5050 MISSION BLVD ONTARIO CA 92761 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 436,273.60 173,486.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 436,273.60 173,486.60 5. Mobilization 23,750.00 0.00 6. Total Work Completed 460,023.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 460,023.60 173,486.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,486.60