Dept. of Trans. PROGRESS Serial No. Contract No. 24-143-08-58 12-0T5904 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 12-ORA-57-11.4/11.7 HSNH-P057(74) Progress payment No. 010 Payment period ending: 05-20-24 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 820,549.00 1,039.50 2. a. Extra Work 17,179.41 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 837,728.41 1,039.50 5. Mobilization 88,000.00 0.00 6. Total Work Completed 925,728.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 925,728.41 1,039.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,039.50