Dept. of Trans. PROGRESS Serial No. Contract No. 24-235-13-57 12-0T9604 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 84% Location: Federal Project: 12-ORA-73-11.4/11.4 NONE Progress payment No. 004 Payment period ending: 08-20-24 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 302,051.00 95,896.00 2. a. Extra Work 3,070.24 330.00 b. Adustment Comp. 78,594.34 78,594.34 3. Materials on Hand 4. Earned Subject to Retention 383,715.58 174,820.34 5. Mobilization 49,339.00 2,466.95 6. Total Work Completed 433,054.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 433,054.58 177,287.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 177,287.29