Dept. of Trans. PROGRESS Serial No. Contract No. 24-143-13-10 12-0U1704 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 33% Location: Federal Project: 12-ORA-133-9.8/12.6 NONE 12-ORA-261-0.0/3.5 Progress payment No. 002 Payment period ending: 05-20-24 CALMEX ENGINEERING INC 2750 S LILAC AVE BLOOMINGTON CA 92316 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,544,794.12 1,920,051.13 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,544,794.12 1,920,051.13 5. Mobilization 205,000.00 51,250.00 6. Total Work Completed 2,749,794.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,749,794.12 1,971,301.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,971,301.13