Dept. of Trans. PROGRESS Serial No. Contract No. 25-205-09-15 12-0U2404 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 79% Location: Federal Project: 12-ORA-91-R9.8/R18.9 NONE Progress payment No. 008 Payment period ending: 07-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,882,610.76 690,403.85 2. a. Extra Work 26,221.00 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -256,869.14 4. Earned Subject to Retention 3,908,831.76 433,534.71 5. Mobilization 120,000.00 0.00 6. Total Work Completed 4,028,831.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,028,831.76 433,534.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 433,534.71