Dept. of Trans. PROGRESS Serial No. Contract No. 26-295-13-29 12-0V5304 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 13% Location: Federal Project: 12-ORA-73-16.6/16.8 NONE 12-ORA-133-R4.1/R5.6 Progress payment No. 001 Payment period ending: 10-20-26 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 268,891.50 268,891.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 268,891.50 268,891.50 5. Mobilization 51,000.00 51,000.00 6. Total Work Completed 319,891.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 319,891.50 319,891.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 319,891.50