Dept. of Trans. PROGRESS Serial No. Contract No. 07-085-12-52 12-101674 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 21% 12-ORA-5-42.1/44.4 Federal Project: ACNH-005-2(932) I-005-2(932) Progress payment No. 11 Payment period ending: 03-20-07 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,713,585.79 2,893,475.82 2.a. Extra Work 639,640.11 26,031.87 b. Adjustment Comp. 373,083.34 113,547.29 3. Materials on Hand 1,082,173.48 69,549.97 4. Earned Subject to Retention 24,808,482.72 3,102,604.95 5. Mobilization 14,475,000.00 0.00 6. Total Work Completed 38,201,309.24 7. Deductions -16,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,267,482.72 3,102,604.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,102,604.95