Dept. of Trans. PROGRESS Serial No. Contract No. 10-147-08-46 12-101674 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 92% 12-ORA-5-42.1/44.4 Federal Project: ACNH-005-2(932) I-005-2(932) Progress payment No. 51 Payment period ending: 05-20-10 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 159,020,588.69 5,271,499.07 2.a. Extra Work 4,300,780.67 88,255.85 b. Adjustment Comp. 2,961,614.72 169,162.30 3. Materials on Hand 308,010.29 -662,801.40 4. Earned Subject to Retention 166,590,994.37 4,866,115.82 5. Mobilization 19,300,000.00 0.00 6. Total Work Completed 185,582,984.08 7. Deductions -151,000.00 15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 185,739,994.37 4,881,115.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,881,115.82