Dept. of Trans. PROGRESS Serial No. Contract No. 10-270-11-54 12-101674 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 12-ORA-5-42.1/44.4 Federal Project: ACNH-005-2(932) I-005-2(932) Progress payment No. 55 Payment period ending: 09-20-10 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 169,427,852.08 1,098,583.42 2.a. Extra Work 4,650,218.29 0.00 b. Adjustment Comp. 2,851,261.35 0.00 3. Materials on Hand 4. Earned Subject to Retention 176,929,331.72 1,098,583.42 5. Mobilization 19,300,000.00 0.00 6. Total Work Completed 196,229,331.72 7. Deductions -151,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 196,078,331.72 1,098,583.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,098,583.42