Dept. of Trans. PROGRESS Serial No. Contract No. 11-298-11-01 12-1016A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 51% 12-ORA-5-42.1/44.4 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-20-11 CLEAN CUT LANDSCAPE 8406 N ARMSTRONG CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 304,242.25 14,866.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -3,230.15 4. Earned Subject to Retention 304,242.25 11,635.85 5. Mobilization 25,000.00 1,250.00 6. Total Work Completed 329,242.25 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 329,242.25 12,885.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,885.85