Dept. of Trans. PROGRESS Serial No. Contract No. 03-353-13-59 12-1072U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 27% 12-ORA-133-4.2/8.1 Federal Project: ACST-P133(10) P-P133(10) Progress payment No. 13 Payment period ending: 12-20-03 SEMA CONSTRUCTION INC 2 SOUTH POINTE DRIVE LAKE FOREST CA 92630 Escrow No. 02046 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,418,752.21 558,386.32 2.a. Extra Work 278,684.25 21,973.14 b. Adjustment Comp. 77,841.16 0.00 3. Materials on Hand 55,350.00 0.00 4. Earned Subject to Retention 7,830,627.62 580,359.46 5. Mobilization 1,273,390.63 0.00 6. Total Work Completed 9,048,668.25 7. Deductions 8. a.Contract Retentions -391,531.38 -29,017.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,712,486.87 551,341.49 10. Reduction Amt to Escrow 11. Payment to Escrow 391,530.00 12. Net Pymt. this Estimate 551,341.49