Dept. of Trans. PROGRESS Serial No. Contract No. 05-168-13-55 12-1072U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 67% 12-ORA-133-4.2/8.1 Federal Project: ACST-P133(10) P-P133(10) Progress payment No. 32 Payment period ending: 06-20-05 SEMA CONSTRUCTION INC 2 SOUTH POINTE DRIVE STE 295 LAKE FOREST CA 92630 Escrow No. 02046 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,689,155.03 302,912.68 2.a. Extra Work 703,391.48 32,901.35 b. Adjustment Comp. 999,843.22 107,500.00 3. Materials on Hand 55,350.00 0.00 4. Earned Subject to Retention 14,447,739.73 443,314.03 5. Mobilization 1,340,411.19 0.00 6. Total Work Completed 15,732,800.92 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -722,386.99 -22,165.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,055,763.93 421,148.33 10. Reduction Amt to Escrow 11. Payment to Escrow 722,380.00 12. Net Pymt. this Estimate 421,148.33