Dept. of Trans. PROGRESS Serial No. Contract No. 06-268-09-22 12-1072U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 100% 12-ORA-133-4.2/8.1 Federal Project: ACST-P133(10) P-P133(10) Progress payment No. 47 Payment period ending: 09-20-06 SEMA CONSTRUCTION INC 6 ORCHARD, STE. 150 LAKE FOREST CA 92630 Escrow No. 02046 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,576,237.87 152,611.93 2.a. Extra Work 2,183,383.05 83,976.65 b. Adjustment Comp. 1,707,285.00 -1,233.73 3. Materials on Hand 4. Earned Subject to Retention 21,466,905.92 235,354.85 5. Mobilization 1,340,411.19 0.00 6. Total Work Completed 22,807,317.11 7. Deductions -864.00 10,000.00 8. a.Contract Retentions -1,073,345.30 -11,767.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,733,107.81 233,587.10 10. Reduction Amt to Escrow 11. Payment to Escrow 1,073,340.00 12. Net Pymt. this Estimate 233,587.10