Dept. of Trans. PROGRESS Serial No. Contract No. 06-299-09-08 12-1072U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 12-ORA-133-4.2/8.1 Federal Project: ACST-P133(10) P-P133(10) Progress payment No. 48 Payment period ending: 10-20-06 SEMA CONSTRUCTION INC 6 ORCHARD, STE. 150 LAKE FOREST CA 92630 Escrow No. 02046 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,748,023.26 171,785.39 2.a. Extra Work 2,299,343.83 115,960.78 b. Adjustment Comp. 1,706,617.32 -667.68 3. Materials on Hand 4. Earned Subject to Retention 21,753,984.41 287,078.49 5. Mobilization 1,340,411.19 0.00 6. Total Work Completed 23,094,395.60 7. Deductions -864.00 0.00 8. a.Contract Retentions -1,087,699.22 -14,353.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,005,832.38 272,724.57 10. Reduction Amt to Escrow 11. Payment to Escrow 1,087,690.00 12. Net Pymt. this Estimate 272,724.57